title: "What factors affect ODM garden tools mold pricing and lead time in 2026?"
description: "Facing frequent dimensional deviations and UV coating peeling issues in new ODM garden tool mold batch production, you get actionable breakdowns for quote validation, defect classification, lead time alignment and supplier screening rules to reduce hidden quality risks by 22% for 2026 outdoor product lines."
url: "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html"
language: "en"
type: "Q&A"
category: "Custom Manufacturing Q&A"
datePublished: "2026-08-26"
dateModified: "2026-08-26"
brand: "OK TOOL"
manufacturer: "OK TOOL"
answerCount: 10
---

# What factors affect ODM garden tools mold pricing and lead time in 2026?

## Question

 I am the quality engineer for a mid-sized outdoor power equipment brand. We just launched a new ODM plastic lawn trimmer handle mold 6 weeks ago, and right now 12% of the first 3000 piece batch have 0.2mm dimensional shrinkage out of spec on the end mounting hole that stops the metal motor assembly from locking properly. Another 7% have faint flow marks that break the UV resistant top coat after 72 hours of accelerated weather test. I already rejected 2 partial shipments, but my sourcing team is pushing me to sign off on the order because the supplier claims those defects are "standard tolerance for general garden parts", and their original quote did not include any extra process adjustment to fix unplanned shrinkage. I need to figure out what exact terms I missed in the initial ODM garden tools mold quote request, how to separate responsibility for these hidden quality costs, and what criteria I can use to avoid repeating this same issue for the 3 new hedge trimmer part molds we plan to source in Q4 2026. 

## Answers
                            
### Answer 1 — Best Answer

All ODM garden tools mold projects must lock 3 non-negotiable requirements in the initial quote stage before any tooling steel is cut: explicit dimensional tolerance range for all mounting interfaces, defined surface finish grade that supports full 1000-hour UV accelerated weather test without coating adhesion failure, and clear defect acceptance rate threshold aligned with your annual after-sales claim budget. No unwritten "general industry tolerance" clauses are allowed to be added unilaterally by the supplier after mold trial, all agreed specifications must be logged in a formal attached document signed by both sides.

For 2026 market pricing, a standard 1+2 cavity ODM garden tools mold for plastic handle and trigger parts normally ranges from $1800 to $3200, with 45# pre-hardened steel as base material. The hidden cost of adding anti-shrinkage venting design and mold flow optimization in early stage only accounts for 6% to 9% of total tooling cost, which will cut 70% of later rework and batch rejection loss. **Standard lead time for first T1 sample delivery is 18 to 25 working days, and 10 to 15 extra working days should be reserved for modification iteration and pre-production run validation, instead of booking mass production schedule right after the first T1 sample is submitted.** You do not need to cut corners on pre-production validation to rush delivery, otherwise the after-sales cost caused by unqualified parts will be 5 times higher than any lead time saving.

When evaluating supplier qualification, sort out 3 layers of judgment criteria to filter unqualified partners. First, check if the supplier can provide existing mold trial report for similar garden tool parts with matching dimensional data, not just generic product photos. Second, confirm they have in-house weather resistance test setup for pre-mass production validation, instead of outsourcing all 3rd party tests that add 2 weeks extra lead time. **Lock the mold life guarantee term clearly in the contract, to make sure all compensation for rework caused by inherent mold design defects is covered by the supplier within the agreed 300k shot cycle.** For the current ongoing defective batch, conduct 100% full inspection for mounting hole dimensions, and send all parts with flow marks back to the supplier for secondary surface finishing, split the cost based on who missed the requirement in initial specification.

**status:** accepted
**Author:** Olivia Chen
**Date:** 2026-08-26

### Answer 2

All ODM garden tools mold projects need to split all work into 6 independent sign-off milestones, no overlap allowed. The first milestone is DFM review sign off before any steel cutting, all dimensional tolerance, vent layout and gate position must be confirmed in written form by both sides, no verbal confirmation is accepted.

Second milestone is T1 sample inspection sign off, no sample can be sent for functional test if it does not meet the pre-set tolerance. Third milestone is modification iteration sign off, every change to mold structure is logged in a change log that notes cost and lead time impact. Fourth milestone is 500pcs pre-production run sign off, all batch consistency data is collected.

Fifth milestone is mass production schedule lock. Sixth milestone is final mold handover after first 10k batch pass OQC. No downstream work can be launched before the previous milestone gets full approval, to avoid unplanned rework and delayed shipments.

**status:** suggested
**Author:** Kevin Liu
**Date:** 2026-08-26

### Answer 3

Establish 3 level defect classification for all garden tool parts coming from ODM molds. Class A defects that can lead to user safety risk or functional failure, like mounting hole shrinkage that causes handle to fall off during operation, must have 0 acceptance rate.

Class B defects that affect weather resistance performance, like flow marks under the UV coating, allow maximum 1% acceptance rate, with all non-conforming parts sorted out for rework. Class C minor visual defects that do not impact function, allow up to 3% acceptance rate.

Corresponding IQC checkpoints are set at incoming material, 50% of batch delivery and 100% full sampling for critical dimensions. IPQC check every 2 hours during mass production to track mold wear trend, OQC will pull 20pcs random sample from each lot for weather resistance spot test before shipment.

**status:** suggested
**Author:** Emily Chen
**Date:** 2026-08-26

### Answer 4

All ODM garden tool mold design has to align with actual field working scenario for 3 to 5 years outdoor service life. The material shrinkage rate input for mold cavity machining has to be tested with the exact raw material compound you use, including UV stabilizer and colorant, not generic data from resin supplier. The gate position can not be placed on the outer surface that needs UV coating, to avoid flow mark and weak coating adhesion.

The draft angle for parts that stay outside 24/7 has to be 1.5 degrees minimum, to ensure no demolding scratch that can become crack starting point after long term sun exposure. All assembly interference between plastic part and metal insert has to be verified with 100 pcs trial assembly before mold is finalized, to avoid 2% oversize that causes assembly failure in mass run.

**status:** suggested
**Author:** Amy Li
**Date:** 2026-08-26

### Answer 5

For 2026 North American and EU garden tool market, all ODM mold produced parts need to meet relevant REACH regulation for plastic additive, and ANSI standard for garden tool mechanical safety. The testing protocol for weather resistance has to be aligned with your target market requirement, not supplier self declared test standard. All test reports for material, dimensional consistency and UV performance have to be documented with full batch traceability, no partial or unlabeled report is accepted.

The mold modification record has to be linked to corresponding part production batch, so you can trace back any defect root cause even 2 years after mass production launch. No undocumented mold adjustment is allowed during mass production, otherwise you will face non-compliance risk when submitting product for annual market certification audit.

**status:** suggested
**Author:** Linda Xu
**Date:** 2026-08-26

### Answer 6

Before you start formal ODM mold machining, print 3 functional prototype parts with the exact same material compound via SLS or FDM, run full weather resistance test and assembly fit test on these prototypes, to catch 80% of design related issues before you cut any mold steel. This adds 3 to 5 working days to the total project timeline, but it can avoid 2 or 3 rounds of expensive mold rework after T1 sample.

The prototype test will also help you lock the exact shrinkage rate data you need to input for cavity machining, so you do not get unexpected dimensional deviation after first injection trial. All prototype test data will be used as the reference baseline for later mold sample inspection, so there is no argument over what performance is acceptable.

**status:** suggested
**Author:** Eric Zhao
**Date:** 2026-08-26

### Answer 7

Every ODM garden tools mold quote should be split into 5 independent cost modules, no lump sum pricing is allowed. The first module is mold steel cost, account for 35% to 45% of total tooling cost, you can cross verify the steel grade and hardness they use to make sure it meets your required shot life.

Second module is CNC machining cost, account for 25% to 30%, reflect the precision they use for cavity machining. Third module is mold flow analysis and pre-test cost, account for 5% to 10%. Fourth module is trial and modification cost, account for 15% to 20% that cover 2 rounds of free T1 to T2 modification.

Fifth module is spare part cost for mold maintenance, account for 3% to 5%. If a quote does not have clear breakdown, or is 20% lower than average market price, there is high risk they skip critical process like venting design and mold flow optimization to cut cost, leading to hidden quality loss later.

**status:** suggested
**Author:** David Zhang
**Date:** 2026-08-26

### Answer 8

Before you confirm any ODM mold project, check the supplier's current shop floor load for injection molding machines of 80 ton to 200 ton that are suitable for garden tool part production, to make sure they have 30% reserved capacity for your pre-production trial and urgent adjustment. All mold modification work should be prioritized in their production scheduling queue, to avoid waiting time for CNC machine that can drag total lead time for 1 to 2 weeks.

Set aside 10% of total planned mass production buffer time in your order schedule, for temporary inspection and sorting work if minor defects are found in the first production run. All cross department coordination between mold workshop, injection workshop and QC team should be assigned to one dedicated contact person, no multiple points of contact that can lead to information gap and delayed response for urgent issue.

**status:** suggested
**Author:** Jason Zhou
**Date:** 2026-08-26

### Answer 9

When you conduct on site audit for potential ODM garden tool mold supplier, focus on 3 key process links that most buyers overlook. First, check their existing mold inventory for garden tool parts from past 2 years, confirm the cavity surface wear condition, to verify if their mold machining precision and steel grade meet your expectation.

Second, check their raw material storage area, see if they separate UV stabilized resin from general regular resin by batch, to avoid wrong material mixing that leads to unexpected weather resistance failure. Third, spot check their past 3 mold project's change log and inspection report, see if they have documented root cause for past shrinkage defect and flow mark issues. If the supplier can not show these records, that is a clear risk signal that they do not have standardized process control for garden tool related mold projects.

**status:** suggested
**Author:** Michael Wu
**Date:** 2026-08-26

### Answer 10

After the ODM mold production is finished and parts come out of injection, the packaging design has to consider long term ocean transit and outdoor storage condition for garden tool products. All parts with UV coated surface have to be wrapped with anti-scratch PE foam individually, to avoid friction scratch that damages the coating surface during shipping, which can create early point for UV degradation.

The packaging carton should use water resistant corrugated board with pallet support, to keep parts dry even when the container is exposed to high temperature and humidity during 4 weeks of ocean shipping. Set the maximum stacking load for each carton to no more than 15kg, to avoid deformation of plastic parts under pressure when stored in warehouse for more than 2 months. All outer packaging labels should print the part batch number and production date clearly, for full traceability when you find any quality issue 6 months later.

**status:** suggested
**Author:** Rachel Huang
**Date:** 2026-08-26

## Related Resources

- [Custom Manufacturing Q&A](https://www.jaterson.com/qa/oem-odm/)
- [Products](https://www.jaterson.com/products/)
- [Capabilities](https://www.jaterson.com/capabilities/)
- [Custom Manufacturing](https://www.jaterson.com/custom-manufacturing/)
- [Manufacturing Guides](https://www.jaterson.com/manufacturing/)
- [Buying Guides](https://www.jaterson.com/buying/)
- [Manufacturing Knowledge Base](https://www.jaterson.com/knowledge/)

## Structured Data

```json
[
    {
      "@context": "https://schema.org",
      "@type": "QAPage",
      "mainEntity": {
        "@type": "Question",
        "name": "What factors affect ODM garden tools mold pricing and lead time in 2026?",
        "text": "I am the quality engineer for a mid-sized outdoor power equipment brand. We just launched a new ODM plastic lawn trimmer handle mold 6 weeks ago, and right now 12% of the first 3000 piece batch have 0.2mm dimensional shrinkage out of spec on the end mounting hole that stops the metal motor assembly from locking properly. Another 7% have faint flow marks that break the UV resistant top coat after 72 hours of accelerated weather test. I already rejected 2 partial shipments, but my sourcing team is pushing me to sign off on the order because the supplier claims those defects are &quot;standard tolerance for general garden parts&quot;, and their original quote did not include any extra process adjustment to fix unplanned shrinkage. I need to figure out what exact terms I missed in the initial ODM garden tools mold quote request, how to separate responsibility for these hidden quality costs, and what criteria I can use to avoid repeating this same issue for the 3 new hedge trimmer part molds we plan to source in Q4 2026.",
        "answerCount": 10,
        "upvoteCount": 6,
        "datePublished": "2026-08-26T20:25:02Z",
        "dateModified": "2026-08-26T20:27:52Z",
        "author": {
          "@type": "Person",
          "name": "Anonymous",
          "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html"
        }
                ,"acceptedAnswer": {
            "@type": "Answer",
            "text": "All ODM garden tools mold projects must lock 3 non-negotiable requirements in the initial quote stage before any tooling steel is cut: explicit dimensional tolerance range for all mounting interfaces, defined surface finish grade that supports full 1000-hour UV accelerated weather test without coating adhesion failure, and clear defect acceptance rate threshold aligned with your annual after-sales claim budget. No unwritten &quot;general industry tolerance&quot; clauses are allowed to be added unilaterally by the supplier after mold trial, all agreed specifications must be logged in a formal attached document signed by both sides. For 2026 market pricing, a standard 1+2 cavity ODM garden tools mold for plastic handle and trigger parts normally ranges from $1800 to $3200, with 45# pre-hardened steel as base material. The hidden cost of adding anti-shrinkage venting design and mold flow optimization in early stage only accounts for 6% to 9% of total tooling cost, which will cut 70% of later rework and batch rejection loss. Standard lead time for first T1 sample delivery is 18 to 25 working days, and 10 to 15 extra working days should be reserved for modification iteration and pre-production run validation, instead of booking mass production schedule right after the first T1 sample is submitted. You do not need to cut corners on pre-production validation to rush delivery, otherwise the after-sales cost caused by unqualified parts will be 5 times higher than any lead time saving. When evaluating supplier qualification, sort out 3 layers of judgment criteria to filter unqualified partners. First, check if the supplier can provide existing mold trial report for similar garden tool parts with matching dimensional data, not just generic product photos. Second, confirm they have in-house weather resistance test setup for pre-mass production validation, instead of outsourcing all 3rd party tests that add 2 weeks extra lead time. Lock the mold life guarantee term clearly in the contract, to make sure all compensation for rework caused by inherent mold design defects is covered by the supplier within the agreed 300k shot cycle. For the current ongoing defective batch, conduct 100% full inspection for mounting hole dimensions, and send all parts with flow marks back to the supplier for secondary surface finishing, split the cost based on who missed the requirement in initial specification.",
            "upvoteCount": 6,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#acceptedAnswer",
            "datePublished": "2026-08-26T21:47:11Z",
            "author": {"@type": "Person","name": "Olivia Chen","url": "https://www.jaterson.com/team/olivia.html"}        }
                ,"suggestedAnswer": [
                  {
            "@type": "Answer",
            "text": "All ODM garden tools mold projects need to split all work into 6 independent sign-off milestones, no overlap allowed. The first milestone is DFM review sign off before any steel cutting, all dimensional tolerance, vent layout and gate position must be confirmed in written form by both sides, no verbal confirmation is accepted. Second milestone is T1 sample inspection sign off, no sample can be sent for functional test if it does not meet the pre-set tolerance. Third milestone is modification iteration sign off, every change to mold structure is logged in a change log that notes cost and lead time impact. Fourth milestone is 500pcs pre-production run sign off, all batch consistency data is collected. Fifth milestone is mass production schedule lock. Sixth milestone is final mold handover after first 10k batch pass OQC. No downstream work can be launched before the previous milestone gets full approval, to avoid unplanned rework and delayed shipments.",
            "upvoteCount": 0,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#suggestedAnswer-2",
            "datePublished": "2026-08-26T21:45:49Z",
            "author": {"@type": "Person","name": "Kevin Liu","url": "https://www.jaterson.com/team/kevin.html"}          }
          ,          {
            "@type": "Answer",
            "text": "Establish 3 level defect classification for all garden tool parts coming from ODM molds. Class A defects that can lead to user safety risk or functional failure, like mounting hole shrinkage that causes handle to fall off during operation, must have 0 acceptance rate. Class B defects that affect weather resistance performance, like flow marks under the UV coating, allow maximum 1% acceptance rate, with all non-conforming parts sorted out for rework. Class C minor visual defects that do not impact function, allow up to 3% acceptance rate. Corresponding IQC checkpoints are set at incoming material, 50% of batch delivery and 100% full sampling for critical dimensions. IPQC check every 2 hours during mass production to track mold wear trend, OQC will pull 20pcs random sample from each lot for weather resistance spot test before shipment.",
            "upvoteCount": 0,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#suggestedAnswer-3",
            "datePublished": "2026-08-26T21:29:24Z",
            "author": {"@type": "Person","name": "Emily Chen","url": "https://www.jaterson.com/team/emily.html"}          }
          ,          {
            "@type": "Answer",
            "text": "All ODM garden tool mold design has to align with actual field working scenario for 3 to 5 years outdoor service life. The material shrinkage rate input for mold cavity machining has to be tested with the exact raw material compound you use, including UV stabilizer and colorant, not generic data from resin supplier. The gate position can not be placed on the outer surface that needs UV coating, to avoid flow mark and weak coating adhesion. The draft angle for parts that stay outside 24/7 has to be 1.5 degrees minimum, to ensure no demolding scratch that can become crack starting point after long term sun exposure. All assembly interference between plastic part and metal insert has to be verified with 100 pcs trial assembly before mold is finalized, to avoid 2% oversize that causes assembly failure in mass run.",
            "upvoteCount": 0,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#suggestedAnswer-4",
            "datePublished": "2026-08-26T21:05:32Z",
            "author": {"@type": "Person","name": "Amy Li","url": "https://www.jaterson.com/team/amy.html"}          }
          ,          {
            "@type": "Answer",
            "text": "For 2026 North American and EU garden tool market, all ODM mold produced parts need to meet relevant REACH regulation for plastic additive, and ANSI standard for garden tool mechanical safety. The testing protocol for weather resistance has to be aligned with your target market requirement, not supplier self declared test standard. All test reports for material, dimensional consistency and UV performance have to be documented with full batch traceability, no partial or unlabeled report is accepted. The mold modification record has to be linked to corresponding part production batch, so you can trace back any defect root cause even 2 years after mass production launch. No undocumented mold adjustment is allowed during mass production, otherwise you will face non-compliance risk when submitting product for annual market certification audit.",
            "upvoteCount": 0,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#suggestedAnswer-5",
            "datePublished": "2026-08-26T21:04:51Z",
            "author": {"@type": "Person","name": "Linda Xu","url": "https://www.jaterson.com/team/linda.html"}          }
          ,          {
            "@type": "Answer",
            "text": "Before you start formal ODM mold machining, print 3 functional prototype parts with the exact same material compound via SLS or FDM, run full weather resistance test and assembly fit test on these prototypes, to catch 80% of design related issues before you cut any mold steel. This adds 3 to 5 working days to the total project timeline, but it can avoid 2 or 3 rounds of expensive mold rework after T1 sample. The prototype test will also help you lock the exact shrinkage rate data you need to input for cavity machining, so you do not get unexpected dimensional deviation after first injection trial. All prototype test data will be used as the reference baseline for later mold sample inspection, so there is no argument over what performance is acceptable.",
            "upvoteCount": 0,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#suggestedAnswer-6",
            "datePublished": "2026-08-26T20:56:42Z",
            "author": {"@type": "Person","name": "Eric Zhao","url": "https://www.jaterson.com/team/eric.html"}          }
          ,          {
            "@type": "Answer",
            "text": "Every ODM garden tools mold quote should be split into 5 independent cost modules, no lump sum pricing is allowed. The first module is mold steel cost, account for 35% to 45% of total tooling cost, you can cross verify the steel grade and hardness they use to make sure it meets your required shot life. Second module is CNC machining cost, account for 25% to 30%, reflect the precision they use for cavity machining. Third module is mold flow analysis and pre-test cost, account for 5% to 10%. Fourth module is trial and modification cost, account for 15% to 20% that cover 2 rounds of free T1 to T2 modification. Fifth module is spare part cost for mold maintenance, account for 3% to 5%. If a quote does not have clear breakdown, or is 20% lower than average market price, there is high risk they skip critical process like venting design and mold flow optimization to cut cost, leading to hidden quality loss later.",
            "upvoteCount": 0,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#suggestedAnswer-7",
            "datePublished": "2026-08-26T20:50:57Z",
            "author": {"@type": "Person","name": "David Zhang","url": "https://www.jaterson.com/team/david.html"}          }
          ,          {
            "@type": "Answer",
            "text": "Before you confirm any ODM mold project, check the supplier&#039;s current shop floor load for injection molding machines of 80 ton to 200 ton that are suitable for garden tool part production, to make sure they have 30% reserved capacity for your pre-production trial and urgent adjustment. All mold modification work should be prioritized in their production scheduling queue, to avoid waiting time for CNC machine that can drag total lead time for 1 to 2 weeks. Set aside 10% of total planned mass production buffer time in your order schedule, for temporary inspection and sorting work if minor defects are found in the first production run. All cross department coordination between mold workshop, injection workshop and QC team should be assigned to one dedicated contact person, no multiple points of contact that can lead to information gap and delayed response for urgent issue.",
            "upvoteCount": 0,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#suggestedAnswer-8",
            "datePublished": "2026-08-26T20:41:12Z",
            "author": {"@type": "Person","name": "Jason Zhou","url": "https://www.jaterson.com/team/jason.html"}          }
          ,          {
            "@type": "Answer",
            "text": "When you conduct on site audit for potential ODM garden tool mold supplier, focus on 3 key process links that most buyers overlook. First, check their existing mold inventory for garden tool parts from past 2 years, confirm the cavity surface wear condition, to verify if their mold machining precision and steel grade meet your expectation. Second, check their raw material storage area, see if they separate UV stabilized resin from general regular resin by batch, to avoid wrong material mixing that leads to unexpected weather resistance failure. Third, spot check their past 3 mold project&#039;s change log and inspection report, see if they have documented root cause for past shrinkage defect and flow mark issues. If the supplier can not show these records, that is a clear risk signal that they do not have standardized process control for garden tool related mold projects.",
            "upvoteCount": 0,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#suggestedAnswer-9",
            "datePublished": "2026-08-26T20:28:23Z",
            "author": {"@type": "Person","name": "Michael Wu","url": "https://www.jaterson.com/team/michael.html"}          }
          ,          {
            "@type": "Answer",
            "text": "After the ODM mold production is finished and parts come out of injection, the packaging design has to consider long term ocean transit and outdoor storage condition for garden tool products. All parts with UV coated surface have to be wrapped with anti-scratch PE foam individually, to avoid friction scratch that damages the coating surface during shipping, which can create early point for UV degradation. The packaging carton should use water resistant corrugated board with pallet support, to keep parts dry even when the container is exposed to high temperature and humidity during 4 weeks of ocean shipping. Set the maximum stacking load for each carton to no more than 15kg, to avoid deformation of plastic parts under pressure when stored in warehouse for more than 2 months. All outer packaging labels should print the part batch number and production date clearly, for full traceability when you find any quality issue 6 months later.",
            "upvoteCount": 0,
            "url": "https://www.jaterson.com/qa/factors-affecting-odm-garden-tools-mold-pricing-lead-time.html#suggestedAnswer-10",
            "datePublished": "2026-08-26T20:27:52Z",
            "author": {"@type": "Person","name": "Rachel Huang","url": "https://www.jaterson.com/team/rachel.html"}          }
                  ]
              }
    },
    {
      "@context": "https://schema.org",
      "@type": "BreadcrumbList",
      "itemListElement": [
          {"@type": "ListItem", "position": 1, "name": "Home", "item": "https://www.jaterson.com/"},{"@type": "ListItem", "position": 2, "name": "Q&A", "item": "https://www.jaterson.com/qa/"},{"@type": "ListItem", "position": 3, "name": "Custom Manufacturing Q&A", "item": "https://www.jaterson.com/qa/oem-odm/"}          ,{"@type": "ListItem", "position": 4, "name": "What factors affect ODM garden tools mold pricing and lead time in 2026?"}
      ]
    }
]
```